ProjectWise Project Insights Help

Task Retrospective tab

The Task Retrospective tab shows information about completed tasks, and contains these charts:

  • Were Tasks completed on time? - Shows how many tasks were completed on time (less than 1 week before the due date; less than 3 weeks before the due date; less than 5 weeks before the due date), and how many tasks were completed late (less than 1 week after the due date; less than 3 weeks after the due date; less than 5 weeks after the due date; more than 5 weeks after the due date).
  • What % of completed Tasks were completed late? - Shows what percentage of completed tasks were completed late (less than 1 week after the due date; less than 3 weeks after the due date; less than 5 weeks after the due date; more than 5 weeks after the due date).
  • Present completed Tasks by latency and discipline - Shows the number of tasks that have been completed so far, grouped by how many weeks past the due date they were completed (latency) and the associated discipline.
  • How many Tasks were completed vs planned to be completed? - Shows the number of tasks that were planned to be completed compared to the number of those tasks that were actually completed.
  • What Tasks are complete? - Shows the list of tasks that are complete. You can sort the list by Due Date, Latency (how late), Completed Date, Discipline, Workflow State.

You can filter the Task Retrospective tab by:

  • Task ID
  • Subtask ID
  • Task Name
  • Discipline
  • Document Name
  • Document Latency
  • Workflow State
  • Task Urgency
  • Task Latency
Note: To display Task ID / Task Number, Task Due Date, Task Completed Date information on this tab, your administrator must assign a ProjectWise attribute to each of the related dimensions on the Pick ProjectWise Attributes settings page.