The following scenarios are possible when modifying
L-Frame supports.
L-Frame - Pipe moved away from vertical leg of L-Frame
In
OpenPlant Modeler, pipe is moved 150mm away from
vertical leg of the L-Frame:
Select Modify Frame, select the frame, and enter:
This will increase the length of the L-Frame by 150mm away from the
vertical leg, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Pipe moved towards the vertical leg of the
L-Frame
In
OpenPlant Modeler, pipe is moved 250mm towards
the vertical leg of the L-Frame:
Select Modify Frame, select the frame, and enter:
This will decrease the length of the L-Frame by 250mm towards the
vertical leg, and move the pipe connect point 250mm.
After pressing
OK, the cantilever should now be correct:
L-Frame - Pipe moved away from the structure
In
OpenPlant Modeler, pipe is moved 150mm away from
the structure:
Select Modify Frame, select the frame, and enter:
This will increase the height of the L-Frame by 150mm away from the
structure, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Pipe moved towards the structure
In
OpenPlant Modeler, pipe is moved 250mm towards
the structure:
Select Modify Frame, select the frame, and enter:
This will decrease the height of the L-Frame by 250mm towards the
structure, and move the pipe connect point 250mm.
After pressing
OK, the frame should now be correct:
L-Frame - Structure moved horizontally away from pipe
In
OpenPlant Modeler, structure is moved 150mm
horizontally away from the pipe:
Select Modify Frame, select the frame, and enter:
This will increase the length of the L-Frame by 150mm away from the
pipe, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Structure moved horizontally towards the pipe
In
OpenPlant Modeler, structure is moved 150mm
horizontally towards the pipe:
Select Modify Frame, select the frame, and enter:
This will decrease the length of the L-Frame by 150mm towards the
pipe, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Structure moved vertically away from the pipe
In
OpenPlant Modeler, structure is moved 150mm
vertically away from the pipe:
Select Modify Frame, select the frame, and enter:
This will increase the height of the L-Frame by 150mm away from the
pipe, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Structure moved vertically towards the pipe
In
OpenPlant Modeler, pipe is moved 150mm vertically
towards the pipe:
Select Modify Frame, select the frame, and enter:
This will decrease the length of the L-Frame by 150mm towards the
pipe, and move the pipe connect point 150mm.
After pressing
OK, the frame should now be correct:
L-Frame - Change length of the horizontal member (pipe and
structure stationary)
Select Modify Frame, select the frame, and enter:
This will increase the length of the beam by 150mm away from the
vertical member.
After pressing
OK, the frame should look like this:
Note: The same method can be used to shorten the length of the
horizontal member.
L-Frame - Change shoe height (pipe did not move)
Select Modify Frame, select the frame, and enter:
This will increase the shoe height by 100mm by increasing the height
of the frame away from the structure.
After pressing
OK, the cantilever should look like this:
L-Frame - Change shoe height (pipe moved)
In
OpenPlant Modeler, the pipe was moved 100mm up,
and the frame is to stay in place, but a shoe will be added:
Select Modify Frame, select the frame, and enter:
This will move the pipeCL Connector of the frame to the correct
location:
After pressing
OK, the cantilever should look like this: