Status Visualization Configuration
The status visualization configuration values are uploaded to the ConstructSim Work Package Server when the data is imported.
Since the status visualization configuration already is aligned with the data, you cannot change the values of the settings.
Before you view the status visualizations, from Run Status Update to align any new data with the status visualization settings. This ensures that you see the most current status visualization information.
you should clickWhenever a user modifies a Value, you need to select the Status Type and click Run Status Update. For example, if some IWP tasks are completed and you want to see the current Pipe Installation Work Package Progress, you need to run the status update in order to see the current status visualization information. In the case of Isometric Release, if you go to the respective EWP Isometrics data and change the Hold value to Yes, you need to run the status update for Isometric Release to see the change.