Construction Work Packages window
Create work package button
Opens the Define the new work package window, which allows you to create a new work package.
Mark as completed > Mark as completed
Turn on one or all (top of the column) of the check boxes to mark the work package as completed.
Mark as completed > Export package
Once the work package is compressed and exported, you have the option of opening or saving the file.
Mark as completed > Delete package
After you select Yes in the Delete confirmation window, the work package is deleted.
Mark as completed > Set properties
Opens an Edit Work Package dialog, which allows you to set personnel and CWA.
Mark as completed > Set progress
Opens an Edit Work Package dialog, which allows you to set a percentage for the progress of the work package.
Show disciplines
You can see all work packages of the selected activity type (Show all) or you can choose to view the work packages in specific disciplines such as Pipe or Steel. After making your selection, select Refresh list to see just the work packages of the discipline(s) you selected.
Check box for multiple selection
The check box at the left end of the row allows you to choose multiple work packages for selection. Turn on the check box at the top of the left column to select all work packages on the current page.
Status
Displays the status of the work package (as set in the General Information tab of the New work package - <package type> window).
Baseline estimated hours
Displays the estimated baseline hours needed for the completion of the work package.
Labor estimated hours
Displays the estimated labor hours needed for the completion of the work package.
Progress
Displays the progress (as set in the Tasks tab of the <Title - Description of work package> window).