To Update the Progress of the Tasks
- From the Work packaging panel, select a work package category such as Installation work packages. This procedure also can be used for the other types of work packages.
- From the Installation Work Packages window, select the work package for which you want to update task hours. The <Title - Description of Work Package> window opens.
- Select Update progress. The Tasks tab opens and displays a list of tasks in the work package grouped by Drawing and Component.
- In the Complete column, click the check box for each task you want to mark as complete.
- Select Save changes. The percentage completed in the Drawing column, the color of the border, and the Overall work progress from the General information tab update automatically.
- (Optional)
Update the actual hours for the task.
The updated hours and PF (Performance Factor) ratio display in the General information tab.