Recording a Contractor's Compensation Event Notification
- From the Contract Communication tile, select New communication. The New communication page appears.
- In the Select communication type box, select Contractor's compensation event notification.
- Enter a descriptive Title in the box.
- Select the Initiated date by clicking the calendar icon ( ), and then selecting a date.
- Click Save changes. The communication page opens to the Attributes tab.
- Enter Details about the communication.
- Select the applicable phrase from the Clause 61.3 - Compensation event clause 60.1 sub-paragraph list.
- Select the Event started to occur on date by clicking the calendar icon ( ), and then selecting a date.
- Select a Communication status from the list.
- Select the Date issued date by clicking the calendar icon ( ), and then selecting a date.
- You can associate additional objects to the communication, such as other communications, documents, files, and notes. For more information see Adding Objects to Communications.
- From the Work Task menu, select Accept.