To Update Information on an EWN Review Task
When you have been
assigned a task for review based on an Early Warning Notification, you must
enter the details about the work that was performed to rectify the situation.
All assigned tasks appear in your Work in Progress folder.
- On the Work Exchange tile, select Work in progress. The Work Exchange folder appears. By default displays all assigned work tasks that have been assigned to you.
- Open a task from the list. Its Communication page opens to the Attributes tab.
- In the Contractor's early warning notification section, describe the details of the notification.
- In the Clause 16.1 - The event could: box, select one or more phrases that best suit the cause of this notification such asDelay completion, Delay meeting a Key Date, or Increase the Contractor's cost, for example.
- Select the severity of this EWN as it pertains to its impact on cost, time, and/or performance. Select either Low, Medium, or High.