Defects Related Communications
Defects related communications are notifications for which the supervisor and contractor notifiy each other as soon as either is aware of a defect that has occurred during the course of a contract. At an agreed upon date, the project Supervisor will list any uncorrected defects or certify that there are no defects, via a defect certificate.
Contractor Defects Related Communications
The following chart depicts the workflow for a Contractor initiated Defects Related Communication:
The steps involved are as follows:
- Contractor initiates the communication
- If a review is required, then an Internal Review is performed.
- The CDN is issued.
Supervisor Defects Related Communications
The following chart depicts the workflow for a Supervisor initiated Defects Related Communication:
The steps involved are as follows: